1.
|
Compare and contrast Material Requirements Planning (MRP) with
Manufacturing Resource Planning (MRPII). (I, II, III)
|
2.
|
Explain the concept and logic of the MRP gross to net requirements
netting process. (II)
|
3.
|
Define the various types of bills of materials and explain their
importance to the MRP planning process. (IV)
|
4.
|
Explain the importance of inventory accuracy to the successful
execution of the material requirements plan. (V)
|
5.
|
Develop a master production schedule and explain how it drives the MRP
system. (VI)
|
6.
|
Interpret specific planned order releases and reschedule notices and
the action/exception messages generated when the MRP system is out of
balance. (VII, VIII)
|
7.
|
Describe the role of capacity requirements planning in an MRP system.
(IX)
|
8.
|
Demonstrate techniques to manage priority planning and priority
control execution. (X, XI, XII)
|
9.
|
Compare and contrast regenerative MRP with net change MRP processing
methods. (XIII)
|
10.
|
Define the requirements and necessary steps to successfully implement
and MRP system. (XIV, XV)
|
|