Field Routing and Vessel Trim |
||
|
Field run specifications, rigging equipment needs, load weights, assembly systems and support needs. Also includes fabricating field run piping and vessel trim. Prerequisites: Registered apprentice status or permission of the Apprenticeship Coordinator. |
||
|
|
||
Go to Competencies Go to Outline
|
MCCCD Official Course Competencies: |
|
|
|
|
|
IMC148 2010 Spring - 9999 |
Field Routing and
Vessel Trim |
1. Describe
the procedures and techniques required to secure a work area to field-route
pipe. (I)
2. Explain
specific methods for determining field run specifications. (II)
3. Given
weight, location and configuration of a job, determine required rigging
equipment. (III)
4. Identify
specific types of erection connections and list the materials required for
these connections. (IV)
5. Demonstrate
screw pipe, socket weld pipe and butt weld pipe assembly systems and list
specific applications of each. (V)
6. Fabricate
and test field run piping. (VI)
7. Erect
specific vessel trim. (VII)
Go to Description Go to top of Competencies
|
MCCCD Official Course Outline: |
|
|
|
|
|
IMC148 2010 Spring - 9999 |
Field Routing and
Vessel Trim |
I. Securing
Work Area
A. Safety
B. Transportation
C. Storage
II. Field
Run Specifications
A. Start/End
Points
B. Check
Area
C. Measure
D. Check
Connections
E. Check
Pipe and In-Line Equipment
III. Rigging
Equipment
A. Load
Calculations
B. Support
Needs
IV. Erection
Materials
A. Common
Types
1. Flange
bolts
2. Gaskets
3. Welding
rods
B. Selecting
Flange Bolts
1. Thread
standards and series
2. Thread
class
3. Thread
designation
4. Fastener
grade
C. Selecting
Flange Gaskets
1. Gasket
materials
2. Types
D. Selecting
Welding rods
V. Assembling
Pipe
A. Screw
Pipe Assembly
B. Socket
Weld Pipe Assembly
C. Butt
Weld Pipe Assembly
VI. Fabricating
Field Run
A. Transporting
and Erecting Piping
B. Testing
1. Test
blinds
2. Hydrotest spools
VII. Vessel Trim
A. Vents
B. Drains
C. Valves
D. Instruments
1. Level
controllers
2. Level
glasses
3. Temperature
elements
E. Erection